PPD CONSTRUCTION ADMINISTRATION PHASE CHECKLIST
PPD REVISED: APRIL 11, 2016
CM/GC SHALL BE RESPONSIBLE FOR FOLLOWING INSPECTIONS AND REVIEWS AND OBTAINING PPD APPROVAL FOR THE BUILDING SUB-SYSTEM FOR SUBSTANTIAL COMPLETION.
20 |
LANDSCAPING AND SOLID WASTE MANAGEMENT |
APPROVED FOR SUBSTANTIAL COMPLETION: (REQUIRED FOR SUBSTANTIAL COMPLETION APPROVAL BY PPD OFFICE.) |
|
---|---|---|---|
INSPECTION/REVIEW ITEM |
NOTICE REQUIRED |
REMARKS |
|
1 | Tree Barricades | Prior to site mobilization | Contractor erects barricades as shown on the Tree Barricade Plan, then call for inspection. |
2 | Digging within Barricades Trimming overhanging limbs |
Prior to the start of work | Contactor calls PPD Grounds before moving barricades or entering the barricaded area to dig. Limbs that are blocking access to work areas may be trimmed with PPD consultation. |
3 | Preserved/Saved landscaping | 48 hours prior to new install. | Final inspection of preserved vegetation before installation of new landscaping is required. |
4 | New Landscaping | Immediately after install. | Contractor provides evidence of correct plant material location, size, species, quality and quantity. |
Solid Waste Management |
|||
5 | Waste management mockup | 72 hours prior to hardscape installation | Stake out a mockup of driveway/access way and call for test run with PPD’s waste management truck. |
6 | Waste management infrastructure | Within 72 hours after hardscape installation has dried | Verification of final construction adequacy, accessibility to servicing equipment at the refuse/recycling facilities. |