PPD CONSTRUCTION ADMINISTRATION PHASE CHECKLIST

PPD REVISED: APRIL 11, 2016
CM/GC SHALL BE RESPONSIBLE FOR FOLLOWING INSPECTIONS AND REVIEWS AND OBTAINING PPD APPROVAL FOR THE BUILDING SUB-SYSTEM FOR SUBSTANTIAL COMPLETION.

 

20

LANDSCAPING AND SOLID WASTE MANAGEMENT

  APPROVED FOR SUBSTANTIAL COMPLETION:

(REQUIRED FOR SUBSTANTIAL COMPLETION APPROVAL BY PPD OFFICE.)
 
INSPECTION/REVIEW ITEM
NOTICE REQUIRED
REMARKS
1 Tree Barricades Prior to site mobilization Contractor erects barricades as shown on the Tree Barricade Plan, then call for inspection.
2 Digging within Barricades
Trimming overhanging limbs
Prior to the start of work Contactor calls PPD Grounds before moving barricades or entering the barricaded area to dig.
Limbs that are blocking access to work areas may be trimmed with PPD consultation.
3 Preserved/Saved landscaping 48 hours prior to new install. Final inspection of preserved vegetation before installation of new landscaping is required.
4 New Landscaping Immediately after install. Contractor provides evidence of correct plant material location, size, species, quality and quantity.
 
Solid Waste Management
   
5 Waste management mockup 72 hours prior to hardscape installation Stake out a mockup of driveway/access way and call for test run with PPD’s waste management truck.
6 Waste management infrastructure Within 72 hours after hardscape installation has dried Verification of final construction adequacy, accessibility to servicing equipment at the refuse/recycling facilities.

 