PPD CONSTRUCTION ADMINISTRATION PHASE CHECKLIST
PPD REVISED: APRIL 11, 2016
CM/GC SHALL BE RESPONSIBLE FOR FOLLOWING INSPECTIONS AND REVIEWS AND OBTAINING PPD APPROVAL FOR THE BUILDING SUB-SYSTEM FOR SUBSTANTIAL COMPLETION.
18 |
DOOR HARDWARE AND KEYS |
APPROVED FOR SUBSTANTIAL COMPLETION: (REQUIRED FOR SUBSTANTIAL COMPLETION APPROVAL BY PPD OFFICE.) |
|
---|---|---|---|
INSPECTION/REVIEW ITEM |
NOTICE REQUIRED |
REMARKS |
|
1 | Submission of door hardware schedule to key shop Cylinders and master keys to be picked up at key shop by GM for contractor install |
Submit following 100% CD approval Prior to door hardware installation |
Approval of the hardware schedule is required prior to the contractor ordering the hardware |
2 | Hardware Inspection: Locksets and Trim Panic Systems and Trim Door Closers ADA door devices |
48 hours prior to installation | All hardware must be available for PPD inspection to ensure the hardware meet the requirements of the UF Design and Construction Standards |
3 | Verify operation and installation workmanship on all items in inspection 2 | Within 48 hours after installation |