PPD CONSTRUCTION ADMINISTRATION PHASE CHECKLIST

PPD REVISED: APRIL 11, 2016
CM/GC SHALL BE RESPONSIBLE FOR FOLLOWING INSPECTIONS AND REVIEWS AND OBTAINING PPD APPROVAL FOR THE BUILDING SUB-SYSTEM FOR SUBSTANTIAL COMPLETION.

 

18

DOOR HARDWARE AND KEYS

  APPROVED FOR SUBSTANTIAL COMPLETION:

(REQUIRED FOR SUBSTANTIAL COMPLETION APPROVAL BY PPD OFFICE.)
 
INSPECTION/REVIEW ITEM
NOTICE REQUIRED
REMARKS
1 Submission of door hardware schedule to key shop
Cylinders and master keys to be picked up at key shop by GM for contractor install
Submit following 100% CD approval
Prior to door hardware installation
Approval of the hardware schedule is required prior to the contractor ordering the hardware
2 Hardware Inspection:
Locksets and Trim
Panic Systems and Trim
Door Closers
ADA door devices
48 hours prior to installation All hardware must be available for PPD inspection to ensure the hardware meet the requirements of the UF Design and Construction Standards
3 Verify operation and installation workmanship on all items in inspection 2 Within 48 hours after installation  

 