PPD CONSTRUCTION ADMINISTRATION PHASE CHECKLIST
PPD REVISED: APRIL 11, 2016
CM/GC SHALL BE RESPONSIBLE FOR FOLLOWING INSPECTIONS AND REVIEWS AND OBTAINING PPD APPROVAL FOR THE BUILDING SUB-SYSTEM FOR SUBSTANTIAL COMPLETION.
16 |
ROOFING AND BUILDING ENVELOPE |
APPROVED FOR SUBSTANTIAL COMPLETION: (REQUIRED FOR SUBSTANTIAL COMPLETION APPROVAL BY PPD OFFICE.) |
|
---|---|---|---|
INSPECTION/REVIEW ITEM |
NOTICE REQUIRED |
REMARKS |
|
1 | Insulation and tapered system in place Drains and drain sump correctly tied into system Wall termination |
24 Hours | |
2 | Base and mid ply application Cap sheet installation All base flashing height, Min 10" higher All roof access doors and hatch flashing min. 12" high |
Inspection 1 + 24 hours | |
3 | At SCI All counter flashing properly installed All solder joints correctly applied All wall cap flashings properly installed All caulking and sealants properly applied Check for standing ponding water (>48 hr) Check that any penetrations are properly sealed Verify that pipes, exhaust vents, equipment, curbs, and the lightning protection system are properly secured |
24 Hours |