PPD CONSTRUCTION ADMINISTRATION PHASE CHECKLIST

PPD REVISED: APRIL 11, 2016
CM/GC SHALL BE RESPONSIBLE FOR FOLLOWING INSPECTIONS AND REVIEWS AND OBTAINING PPD APPROVAL FOR THE BUILDING SUB-SYSTEM FOR SUBSTANTIAL COMPLETION.

 

15

ENERGY MANAGEMENT AND CONTROL SYSTEM

  APPROVED FOR SUBSTANTIAL COMPLETION:

(REQUIRED FOR SUBSTANTIAL COMPLETION APPROVAL BY PPD OFFICE.)
 
INSPECTION/REVIEW ITEM
NOTICE REQUIRED
REMARKS
1 Verify that all hardware is on line to the PPD Energy Management and Control System and is controlled by PPD
Check that all points are reading reliably on Energy Management and Control System
Operate all control points (stop/start, dampers, etc.) to ensure that they operate.
One week prior to SCI  
2 Check that all labels, tags, etc. are in place. One week prior to SCI  

 