PPD CONSTRUCTION ADMINISTRATION PHASE CHECKLIST

PPD REVISED: APRIL 11, 2016
CM/GC SHALL BE RESPONSIBLE FOR FOLLOWING INSPECTIONS AND REVIEWS AND OBTAINING PPD APPROVAL FOR THE BUILDING SUB-SYSTEM FOR SUBSTANTIAL COMPLETION.

 

14

BUILDING FIRE ALARM

  APPROVED FOR SUBSTANTIAL COMPLETION:

(REQUIRED FOR SUBSTANTIAL COMPLETION APPROVAL BY PPD OFFICE.)
 
INSPECTION/REVIEW ITEM
NOTICE REQUIRED
REMARKS
1 Fill out fire alarm data sheet One week The items indicated will be checked along with contractor to ensure proper installation and that all PPD standards have been met before signing off this release.
2 Test all pull stations
Smoke all detectors
Check all horns, speakers and lights
Check all horns, speakers and lights
Check flow switch (if applicable)
Check that wiring matches our color code
Check that wiring is proper type
Run battery test
One week Pull down at least one pull station and one detector. Remove wire and check for trouble indication.
3 Check FAAP Zone Map
Check FAAP for proper operation
One week  
4 Check for FACP protection by a detector
Show location of main junction boxes
Show physical location of any AUX relays
Check that all junction boxes painted red
Check to insure that all detectors are readily accessible.
Check the remote LEDs for the detectors to insure they are visible.
One week


This includes AHU shut down, magnetic doors, etc. These relays should be indicated on the prints.
5 Field check the accuracy of all documents One week  
6 Turn in all keys, tools, etc. for the system One week  

Multiple inspections required for large projects

 