PPD CONSTRUCTION ADMINISTRATION PHASE CHECKLIST
PPD REVISED: APRIL 11, 2016
CM/GC SHALL BE RESPONSIBLE FOR FOLLOWING INSPECTIONS AND REVIEWS AND OBTAINING PPD APPROVAL FOR THE BUILDING SUB-SYSTEM FOR SUBSTANTIAL COMPLETION.
13 |
ELECTRICAL SYSTEMS (INCLUDING TEMPORARY POWER) |
APPROVED FOR SUBSTANTIAL COMPLETION: (REQUIRED FOR SUBSTANTIAL COMPLETION APPROVAL BY PPD OFFICE.) |
|
---|---|---|---|
INSPECTION/REVIEW ITEM |
NOTICE REQUIRED |
REMARKS |
|
Temporary Metering: | |||
1 | Establish billing account with PPD Business Operations Request temporary meter(s) from PPD Utility Administration Department Install temp. meter and accessories Energize temp. power |
14 days 48 hours |
|
Conduit/Ductbank: | |||
2 | Installation has proper depth and slope of 30” below grade Installation of metalized tape |
24 Hours | |
Manholes/Switch Pits: | |||
3 | Design to fit as-built site conditions Proper wrap of cables inside manholes on porcelain insulators off floor on Hot dipped galvanized or stainless steel hardware. All cable not in conduit to be fireproofed with approved tape Grounding and strapping of cables and lid to ¾” ground rod Square or rectangular spring assist covers Gravel in switch pit |
24 Hours | Operations Engineer to verify site conditions and approve any field adjustments as required. Tape should be equivalent to Scotch Brand #7700 |
Medium Voltage Switch: | |||
4 | Gas pressure within range/no apparent leaks Attachments |
24 Hours | Provide one tank of extra SF6 gas at time of Substantial Completion. |
Transformers: | |||
5 | Winding conductor type. Copper Only. Minimum 1 lb PSI pressure shown on gauge. Lightning arrestors Grounds Concrete pad Verify size and accessories |
24 hours | |
Permanent Metering | |||
6 | Verify CT’s Verify PT’s Verify wiring in meter enclosure Verify Correct ELSTER / BYRAM Labs meter |
24 Hours | Meter must be installed prior to energizing. Any questions contact the Electric and Water Metering Technician listed on the UF PPD website under Utilities and Energy Services, Administration and Analysis |
Main Service: | |||
7 | Proper grounding and bonding Labels for all breakers Bonding of main service Testing of breakers / certifications |
24 Hours | Certification paper on main breakers. |
Interior wiring and lights: | |||
8 | Check connections for transformers. Check panel boards Bonding & Grounding GFCI Labels Ceiling lights Ensure all devices have proper covers Verify specified T-8 lamps and electronic ballasts Boxes Check all equipment for paint damage Proper type of connectors, coupling, boxes for raceways Proper strapping of raceways (EMT, conduits) |
24 Hours | Labels for panel boards and all equipment ensure schedules/spares are identified. Panel board covers are “door in door” type. Busses shall be copper. All receptacles and light switches shall be marked by circuit number using numbered vinyl cloth adhesive markers. Boxes above suspended ceilings shall be installed facing down. All covers shall have panel board and circuit number |
Exterior Wiring & Lights: | |||
9 | Ensure all poles are grounded Outdoor equipment Mounting wall fixtures |
24 Hours | |
Emergency Generator: | |||
10 | Check Fuel Level Test start and transfer time Transfer switches Check operation of day tank pump. Turn over all test equipment, i.e. oil bottles, etc. Turn over all test reports |
24 Hours | |
Special Equipment: | |||
11 | Training for electrical equipment Instruction for special equipment Tools or Keys for specialized equipment |
24 Hours | Provide 12 sets of specialized tools or accessory equipment needed to operate the specialized equipment. |
Multiple inspections required for large projects