PPD CONSTRUCTION ADMINISTRATION PHASE CHECKLIST

PPD REVISED: APRIL 8, 2016
CM/GC SHALL BE RESPONSIBLE FOR FOLLOWING INSPECTIONS AND REVIEWS AND OBTAINING PPD APPROVAL FOR THE BUILDING SUB-SYSTEM FOR SUBSTANTIAL COMPLETION.

 

11

BUILDING PLUMBING/FIXTURES

  APPROVED FOR SUBSTANTIAL COMPLETION:

(REQUIRED FOR SUBSTANTIAL COMPLETION APPROVAL BY PPD OFFICE.)
 
INSPECTION/REVIEW ITEM
NOTICE REQUIRED
REMARKS
1 Initial pressure testing of the system 24 Hours Must be witnessed and signed off by PPD Operations Engineering.
2 Piping, valves, drains, leaks 60% Completion Inspections must be conducted before piping is covered
3 Water closet, flush system
Water Closet fixtures
Water fountains
One week prior to SCI  
4 Field/Change orders At all phases See general notes.

 