PPD CONSTRUCTION ADMINISTRATION PHASE CHECKLIST
PPD REVISED: APRIL 8, 2016
CM/GC SHALL BE RESPONSIBLE FOR FOLLOWING INSPECTIONS AND REVIEWS AND OBTAINING PPD APPROVAL FOR THE BUILDING SUB-SYSTEM FOR SUBSTANTIAL COMPLETION.
10 |
SITE/BUILDING FIRE SYSTEMS |
APPROVED FOR SUBSTANTIAL COMPLETION: (REQUIRED FOR SUBSTANTIAL COMPLETION APPROVAL BY PPD OFFICE.) |
|
---|---|---|---|
INSPECTION/REVIEW ITEM |
NOTICE REQUIRED |
REMARKS |
|
1 | Automatic Sprinkler system | 60% & Substantial | In addition to PPD inspections, coordinate for SFM/EHS inspections. |
2 | Controls | 60% & Substantial | In addition to PPD inspections, coordinate for SFM/EHS inspections. |
3 | Fire Pumps | 60% & Substantial | In addition to PPD inspections, coordinate for SFM/EHS inspections. |