PPD CONSTRUCTION ADMINISTRATION PHASE CHECKLIST
PPD REVISED: APRIL 8, 2016
CM/GC SHALL BE RESPONSIBLE FOR FOLLOWING INSPECTIONS AND REVIEWS AND OBTAINING PPD APPROVAL FOR THE BUILDING SUB-SYSTEM FOR SUBSTANTIAL COMPLETION.
9 |
BUILDING POTABLE WATER SYSTEMS |
APPROVED FOR SUBSTANTIAL COMPLETION: (REQUIRED FOR SUBSTANTIAL COMPLETION APPROVAL BY PPD OFFICE.) |
|
---|---|---|---|
INSPECTION/REVIEW ITEM |
NOTICE REQUIRED |
REMARKS |
|
1 | Piping / valve installations. Verify metering. Check Drain System |
60% Completion | |
2 | Flushing & Sterilizing Water Sampling |
24 Hours | Must be witnessed & signed off by PPD Operations Engineering. Must be witnessed by and sampling results returned to PPD Operations Engineering. |
3 | Valve Charts | One week prior to SCI | Must be in a location within the building, framed or laminated. |
4 | Field/Change order | At all phases | See general notes. |