PPD CONSTRUCTION ADMINISTRATION PHASE CHECKLIST

PPD REVISED: APRIL 8, 2016
CM/GC SHALL BE RESPONSIBLE FOR FOLLOWING INSPECTIONS AND REVIEWS AND OBTAINING PPD APPROVAL FOR THE BUILDING SUB-SYSTEM FOR SUBSTANTIAL COMPLETION.

 

9

BUILDING POTABLE WATER SYSTEMS

  APPROVED FOR SUBSTANTIAL COMPLETION:

(REQUIRED FOR SUBSTANTIAL COMPLETION APPROVAL BY PPD OFFICE.)
 
INSPECTION/REVIEW ITEM
NOTICE REQUIRED
REMARKS
1 Piping / valve installations. Verify metering.
Check Drain System
60% Completion  
2 Flushing & Sterilizing
Water Sampling
24 Hours Must be witnessed & signed off by PPD Operations Engineering.
Must be witnessed by and sampling results returned to PPD Operations Engineering.
3 Valve Charts One week prior to SCI Must be in a location within the building, framed or laminated.
4 Field/Change order At all phases See general notes.

 