PPD CONSTRUCTION ADMINISTRATION PHASE CHECKLIST

PPD REVISED: APRIL 8, 2016
CM/GC SHALL BE RESPONSIBLE FOR FOLLOWING INSPECTIONS AND REVIEWS AND OBTAINING PPD APPROVAL FOR THE BUILDING SUB-SYSTEM FOR SUBSTANTIAL COMPLETION.

 

8

SITE UNDERGROUND STEAM & CONDENSATE SYSTEMS

  APPROVED FOR SUBSTANTIAL COMPLETION:

(REQUIRED FOR SUBSTANTIAL COMPLETION APPROVAL BY PPD OFFICE.)
 
INSPECTION/REVIEW ITEM
NOTICE REQUIRED
REMARKS
1 Obtain Dig Permit 72 hours Contractor requests Dig Permit 72 hours prior to digging.
2 Wet Tapping 48 Hours Wet Tap only with approval and in the presence of PPD Operations Engineering.
3 Inspection of pipe installation 24 Hours PPD Operations Engineering to inspect and approve installation (to include proper elevation).
4 Inspection of pipe insulation 24 Hours PPD Operations Engineering to inspect insulation of piping.
5 Warning tape
Inspection of manhole
Inspection of valves
Hydrostatic Pressure Testing of steam and condensate pipes
24 Hours Warning Tape must be placed 12-18” above pipe.
Must be witnessed & signed off by PPD Operations Engineering.
6 Cleaning, Flushing & Pretreatment 24 Hours Must be witnessed & signed off by PPD Operations Engineering and the UF PPD Water Treatment Contractor.
7 Field/Change order Review See general notes.

For new pre-fabricated pre-insulated underground piping, provide one copy of pre-fabricated pre-insulated pipe manufacturer’s submittal to PPD Operations Engineering at or before underground piping installation begins.

Multiple inspections required for large projects

 