PPD CONSTRUCTION ADMINISTRATION PHASE CHECKLIST
PPD REVISED: APRIL 8, 2016
CM/GC SHALL BE RESPONSIBLE FOR FOLLOWING INSPECTIONS AND REVIEWS AND OBTAINING PPD APPROVAL FOR THE BUILDING SUB-SYSTEM FOR SUBSTANTIAL COMPLETION.
7 |
SITE UNDERGROUND CHILLED WATER SYSTEMS |
APPROVED FOR SUBSTANTIAL COMPLETION: (REQUIRED FOR SUBSTANTIAL COMPLETION APPROVAL BY PPD OFFICE.) |
|
---|---|---|---|
INSPECTION/REVIEW ITEM |
NOTICE REQUIRED |
REMARKS |
|
1 | Obtain Dig Permit | 72 hours | Contractor requests Dig Permit 72 hours prior to digging. |
2 | Wet Tapping | 24 Hours | Wet Tap only with approval and in the presence of PPD Operations Engineering. |
3 | Inspection of pipe installation | 24 Hours | PPD Operations Engineering to inspect and approve installation (to include proper elevation). |
4 | Inspection of pipe insulation Warning tape Inspection of manhole Inspection of valves Hydrostatic Pressure Testing of chilled water pipe |
24 Hours | Warning Tape must be placed 12-18” above pipe. Verify conformance with UF Standards. Must be witnessed & signed off by PPD Operations Engineering |
5 | Cleaning, Flushing & Pretreatment | 24 Hours | Must be witnessed & signed off by PPD Operations Engineering and the UF PPD Water Treatment Contractor. |
6 | Field/Change order | All phases | See general notes. |
For new pre-fabricated pre-insulated underground piping, provide one copy of pre-fabricated pre-insulated pipe manufacturer’s submittal to PPD Operations Engineering at or before underground piping installation begins.
Multiple inspections required for large projects