PPD CONSTRUCTION ADMINISTRATION PHASE CHECKLIST

PPD REVISED: APRIL 8, 2016
CM/GC SHALL BE RESPONSIBLE FOR FOLLOWING INSPECTIONS AND REVIEWS AND OBTAINING PPD APPROVAL FOR THE BUILDING SUB-SYSTEM FOR SUBSTANTIAL COMPLETION.

 

6

SITE UNDERGROUND POTABLE WATER SYSTEMS

  APPROVED FOR SUBSTANTIAL COMPLETION:

(REQUIRED FOR SUBSTANTIAL COMPLETION APPROVAL BY PPD OFFICE.)
 
INSPECTION/REVIEW ITEM
NOTICE REQUIRED
REMARKS
1 Obtain Dig Permit 72 hours Contractor requests Dig Permit 72 hours prior to digging.
2 Wet Tapping 48 Hours Wet Tap only with approval and in the presence of PPD Operations Engineering.
3 Piping and thrust blocks/restraints.
Labels and concrete pads for valve box.
BFP indoor & outdoor installation.
Meter/bypass assembly
24 Hours PPD Operations Engineering must inspect installation / thrust blocks or tie rods, etc. prior to back filing trenches. Thrust blocks with visqueen.
PPD Operations Engineering will inspect labeling and concrete pad of the valve box lid.
Call PPD Operations Engineering to inspect and approve installation. Outdoor hot boxes.
Strainer upstream of water meter. Install bypass valve lock. Install UF Master key Lock.
4 Warning tape, Tracing Wire During earth work Tracing wire for PVC must be attached to non-metallic pipe. Warning Tape 12-18” above pipe.
5 Flushing & Sterilizing 24 Hours Must be witnessed & signed off by PPD Operations Engineering.
6 Pressure Testing 24 Hours  
7 Meter pit cleaned of debris
Gravel in meter pit
Meter Certification
One week prior to SCI Remove all sand, debris out of meter box. PPD Operations Engineering will inspect to ensure cleanliness.
Meter must read 0-10 K Gal on certification date.
8 Field/Change order At all phases See general notes.

 