PPD CONSTRUCTION ADMINISTRATION PHASE CHECKLIST

PPD REVISED: APRIL 8, 2016
CM/GC SHALL BE RESPONSIBLE FOR FOLLOWING INSPECTIONS AND REVIEWS AND OBTAINING PPD APPROVAL FOR THE BUILDING SUB-SYSTEM FOR SUBSTANTIAL COMPLETION.

 

5

SITE UNDERGROUND IRRIGATION SYSTEMS

  APPROVED FOR SUBSTANTIAL COMPLETION:

(REQUIRED FOR SUBSTANTIAL COMPLETION APPROVAL BY PPD OFFICE.)
 
INSPECTION/REVIEW ITEM
NOTICE REQUIRED
REMARKS
1 Obtain Dig Permit 72 hours Contractor requests Dig Permit 72 hours prior to digging.
2 New Connections to existing piping
Identification color and markings.
24 Hours New Connections to existing piping must be inspected prior to backfilling
Purple for pipes, sprinkler heads and valve box lids marked as "RECLAIMED WATER"
3 Warning tape, Tracing wire During earth work Tracing wire must be attached to non-metallic pipe. Warning Tape must be placed 12-18" above pipe.
4 Concrete pad around the main valve box. One week prior to SCI  
5 PSI regulating valves
Meter at every connection to reclaimed water or well.
One week prior to SCI On systems with fluctuating PSI.
Install irrigation meter at every connection to campus reclaimed water supply lines.
6 System pressure test (PSI) Prior to any use. The trench may not be backfilled until the pressure test is conducted and verified.
7 Field/Change orders At all phases See general notes.

 