PPD CONSTRUCTION ADMINISTRATION PHASE CHECKLIST
PPD REVISED: APRIL 8, 2016
CM/GC SHALL BE RESPONSIBLE FOR FOLLOWING INSPECTIONS AND REVIEWS AND OBTAINING PPD APPROVAL FOR THE BUILDING SUB-SYSTEM FOR SUBSTANTIAL COMPLETION.
5 |
SITE UNDERGROUND IRRIGATION SYSTEMS |
APPROVED FOR SUBSTANTIAL COMPLETION: (REQUIRED FOR SUBSTANTIAL COMPLETION APPROVAL BY PPD OFFICE.) |
|
---|---|---|---|
INSPECTION/REVIEW ITEM |
NOTICE REQUIRED |
REMARKS |
|
1 | Obtain Dig Permit | 72 hours | Contractor requests Dig Permit 72 hours prior to digging. |
2 | New Connections to existing piping Identification color and markings. |
24 Hours | New Connections to existing piping must be inspected prior to backfilling Purple for pipes, sprinkler heads and valve box lids marked as "RECLAIMED WATER" |
3 | Warning tape, Tracing wire | During earth work | Tracing wire must be attached to non-metallic pipe. Warning Tape must be placed 12-18" above pipe. |
4 | Concrete pad around the main valve box. | One week prior to SCI | |
5 | PSI regulating valves Meter at every connection to reclaimed water or well. |
One week prior to SCI | On systems with fluctuating PSI. Install irrigation meter at every connection to campus reclaimed water supply lines. |
6 | System pressure test (PSI) | Prior to any use. | The trench may not be backfilled until the pressure test is conducted and verified. |
7 | Field/Change orders | At all phases | See general notes. |