PPD CONSTRUCTION ADMINISTRATION PHASE CHECKLIST
PPD REVISED: FEBRUARY 29, 2016
CM/GC SHALL BE RESPONSIBLE FOR FOLLOWING INSPECTIONS AND REVIEWS AND OBTAINING PPD APPROVAL FOR THE BUILDING SUB-SYSTEM FOR SUBSTANTIAL COMPLETION.
3 |
SITE UNDERGROUND SANITARY SYSTEMS |
APPROVED FOR SUBSTANTIAL COMPLETION: (REQUIRED FOR SUBSTANTIAL COMPLETION APPROVAL BY PPD OFFICE.) |
|
---|---|---|---|
INSPECTION/REVIEW ITEM |
NOTICE REQUIRED |
REMARKS |
|
1 | Obtain Dig Permit | 72 hours | Contractor requests Dig Permit 72 hours prior to digging. |
2 | New Manholes/Piping Connections | 24 Hours | Manholes/ Piping connections must be inspected prior to backfilling. |
3 | Drop manhole Connections | 24 Hours | Must be inspected prior to backfilling trenches. |
4 | Warning tape, Tracing Wire Manhole at intersections (Tee) Cleanouts Manholes and catch basins cleaned of debris |
During earth work | Tracing wire must be attached to non-metallic pipe. Warning Tape must be placed 12-18” above pipe. All cleanouts must be available for inspection |
5 | Videotape all new lines 4" and over. | One week prior to SCI | Videos must be provided to the PPD Operations civil engineer one week prior to substantial completion. |
6 | Channel the bottom of manholes. | One week prior to SCI | Videos must be provided to the PPD Operations civil engineer one week prior to substantial completion. |
7 | Field/Change order | At all phases | See general notes. |
For new manholes, provide one copy of manhole manufacturer’s submittal to PPD Operations Engineering at or before underground piping installation begins.