PPD CONSTRUCTION ADMINISTRATION PHASE CHECKLIST

PPD REVISED: FEBRUARY 29, 2016
CM/GC SHALL BE RESPONSIBLE FOR FOLLOWING INSPECTIONS AND REVIEWS AND OBTAINING PPD APPROVAL FOR THE BUILDING SUB-SYSTEM FOR SUBSTANTIAL COMPLETION.

 

3

SITE UNDERGROUND SANITARY SYSTEMS

  APPROVED FOR SUBSTANTIAL COMPLETION:

(REQUIRED FOR SUBSTANTIAL COMPLETION APPROVAL BY PPD OFFICE.)
 
INSPECTION/REVIEW ITEM
NOTICE REQUIRED
REMARKS
1 Obtain Dig Permit 72 hours Contractor requests Dig Permit 72 hours prior to digging.
2 New Manholes/Piping Connections 24 Hours Manholes/ Piping connections must be inspected prior to backfilling.
3 Drop manhole Connections 24 Hours Must be inspected prior to backfilling trenches.
4 Warning tape, Tracing Wire
Manhole at intersections (Tee)
Cleanouts
Manholes and catch basins cleaned of debris
During earth work Tracing wire must be attached to non-metallic pipe. Warning Tape must be placed 12-18” above pipe.
All cleanouts must be available for inspection
5 Videotape all new lines 4" and over. One week prior to SCI Videos must be provided to the PPD Operations civil engineer one week prior to substantial completion.
6 Channel the bottom of manholes. One week prior to SCI Videos must be provided to the PPD Operations civil engineer one week prior to substantial completion.
7 Field/Change order At all phases See general notes.

For new manholes, provide one copy of manhole manufacturer’s submittal to PPD Operations Engineering at or before underground piping installation begins.

 